Castle Hume Golf Clubhouse, Enniskillen

Test all sewer outlets from the Clubhouse and checking all existing sewer locations and invert levels.

New line for sewers and manholes were agreed and levels set up so that piling on the new sewer lines could commence. A 6-inch sewer was laid across car park from pump sump.

A temporary access to Clubhouse was set up and signage erected to minimise disruption to golfers and staff.

The new sewer was laid in the piled area and all trenches backfilled with Type 3 stone and new manholes fitted.

Connection of all existing sewer pipes and 150 PVC sewer was laid in site area and connected, before reinstating all areas disturbed.

 

Customer

Loughshore Road Ltd

What We Did

Laying of New Sewer Line 

Contract Period

8 weeks September – October 2018

Engineer

Kane Design Engineers

Piling Company

Hamilton Bogie